[See rule 65(8)] Form for failure report in respect of Transformers/Reactors of 20 MVA and above

ANNEXURE XV

65. Testing, Operation and Maintenance-

(8) Failures of transformers and reactors of 20 MVA and higher capacity shall be reported by the consumers and the suppliers of electricity within 48 hours of the occurrence of the failure, to the electrical inspector and Central Electricity Board. The reasons for failure and measures to be taken to avoid recurrence of failure shall be sent to the electrical inspector and Central Electricity Board within one month of the occurrence in the format given in Annexure XV.